Mohamed Bin Zayed Center case: SERTEM counterattacks and accuses DER/FJ of serious shortcomings

Auteur: Doudou DIOP

image

Affaire du centre Mohamed Bin Zayed : SERTEM contre-attaque et accuse la DER/FJ de graves manquements

New developments in the dispute between the General Delegation for Rapid Entrepreneurship for Women and Youth (DER/FJ) and the company SERTEM GROUPE! In an aggressive press release published on April 7, 2026, SERTEM's communications unit dismantles point by point the version put forward by the DER in the case of the termination of the contract estimated at 17 billion FCFA, relating to the construction of the Mohamed Bin Zayed Center.

At the heart of the controversy is the accusation that SERTEM abandoned the construction site for nearly 20 months. An allegation the company categorically denies, providing supporting documents. According to SERTEM, there was never a unilateral work stoppage, but rather a suspension governed by contractual provisions, specifically Article 48.3 of the General Administrative Clauses (CCAG), resulting from breaches by the project owner.

The company mentions a precise chronology: a formal notice sent as early as March 2023 for non-payment and lack of exemptions, a continuation of work noted in February 2024, then a suspension in April 2024, before a demobilization that took place in January 2026 after official notification of termination.

But the most sensitive point in the case concerns tax and customs exemptions. SERTEM claims it never received the necessary permits to execute the contract, despite an authorization mentioned by the DER (Delegation for Rapid Entrepreneurship) for 8.3 billion FCFA. This situation has led to a blockage of suppliers, refusals to issue tax-free invoices, and equipment being held up in customs, effectively paralyzing the progress of the construction project.

In its press release, SERTEM raised a key issue: the delay in the approval of the architectural plans. According to the company, these plans were only approved in February 2023, nearly a year after the project's official start. This is a major anomaly for a construction project of this scale. SERTEM maintains that it was physically impossible to meet the deadlines under these circumstances.

On the financial front, the company also points to unpaid amounts exceeding 2.6 billion FCFA, of which more than 2.19 billion were already due before September 2023. It recalls that the contractual payment deadlines are set at 45 days, beyond which late payment interest and a right to suspend work apply.

SERTEM also disputes the DER's argument regarding the 3.4 billion FCFA advance payment. It clarifies that this is a contractual advance equivalent to 20% of the contract, fully guaranteed and intended solely for mobilizing the construction site, not to cover the work already completed. The press release also denounces the DER's silence in the face of numerous letters sent, including formal notices and suspension notifications, which have gone unanswered.

Beyond the technical and financial aspects, SERTEM is challenging the overall management of the project, which it describes as chaotic. It asserts that the tender was launched without the essential conditions being met, notably the absence of effective exemptions and validated plans.

The company also refutes the overall amount of 25.56 billion FCFA including tax put forward by the DER, maintaining that the actual contract amounts to 17.24 billion FCFA excluding tax, and describes the figures communicated as “fanciful”.

Finally, SERTEM questions the conditions of the contract termination and the rapid reassignment of the contract to another company, especially given that legal proceedings are underway. It considers this approach suspicious, particularly since, according to SERTEM, state oversight bodies recommended that the project be withdrawn from the DER (Delegation for Rapid Entrepreneurship).

Auteur: Doudou DIOP
Publié le: Mercredi 08 Avril 2026

Commentaires (4)

  • image
    nay ler il y a 3 jours
    A quoi sert le centre Mohammed bin Zaid ? est un establishment sanitaire au quel cas que fait la DER la dedans ?
  • image
    Passant il y a 3 jours
    En tout cas c’est pas clair ce dossier de sertem et l’état à Dakar tous ces immeubles qui poussent et qui profitent à des lobbys entre le blanchiment de l’argent sale et la drogue et maintenant le lobbying homosexuel Un appartement dans de Dakar premier le prix d’un F2 commence à 100 millions et ça va jusqu’à 400 millions par exemple Dactower quel sénégalais peut acheter ça ?
  • image
    Nianthio il y a 3 jours
    Le bâtiment est connu de tous. Pour un coût total de 17 milliards, l entreprise a déjà injecté 4 milliards. Mais pourquoi Aida mbodj resilie le contrat et donne a une autre entreprise pour 17 milliards. Un bâtiment très avancé, vousle négociez a 17 milliards encore? 4 milliards +17 = 21 milliards Et le propriétaire de la nivelle entreprise est supposé être proche du pouvoir et ne fait que du sous traitement. Il n a aucune qualification
  • image
    YEMAIN il y a 3 jours
    VIVEMENT LA REPRISE DES TRAVAUX PAR SERTEM. BEAUCOUP SONT EN CHÔMAGE A CAUSE DE SITUATIONS SIMILAIRES.

Participer à la Discussion

Règles de la communauté :

  • Soyez courtois. Pas de messages agressifs ou insultants.
  • Pas de messages inutiles, répétitifs ou hors-sujet.
  • Pas d'attaques personnelles. Critiquez les idées, pas les personnes.
  • Contenu diffamatoire, vulgaire, violent ou sexuel interdit.
  • Pas de publicité ni de messages entièrement en MAJUSCULES.

💡 Astuce : Utilisez des emojis depuis votre téléphone ou le module emoji ci-dessous. Cliquez sur GIF pour ajouter un GIF animé. Collez un lien X/Twitter, TikTok ou Instagram pour l'afficher automatiquement.